Civil work for Foundation, Erection of Transmission Towers & Conductor Stringing
Location : Republic of Congo.
Commissioning: October, 2018.
Erection & Commissioning of 1 x 3.15 MW DG Sets at BCPL - Dibrugarh
Location: Dibrugarh, Assam.
Fuel: HFO
DG Set: Kirloskar, 1 No. x 3.15 MW
Commissioning: March, 2014.
Erection & Commissioning of 1 x 2.5 MW DG Sets at IFFCO
Location: Phulpur, U.P.
Fuel: HFO
DG Set: Kirloskar, 1 No. x 2.5 MW
Commissioning: December, 2012.
Erection & Commissioning of 2 x 2.5 MW DG Sets at GNFC
Location: Dahej, Gujarat
Fuel: HFO
DG Set: Kirloskar, 2 Nos. x 2.5 MW
Commissioning: December, 2012.
Dismantling of Existing Flare Stack, Supply of Material & Erection of New Flare Stack.
Location: Navi Mumbai
Fuel: HFO
DG Set: Caterpillar 7 Nos. x 14 MW
Commissioning: May, 2012.
Consultancy, Engineering, Project Management, Erection & Commissioning of HFO based Power Plant for 106 MW for M/s.Powerpac Mutiara.
Location: Keraniganj, Bangladesh
Fuel: HFO
DG Set: Caterpillar 7 Nos. x 14 MW
Commissioning: March, 2012.
Consultancy, Engineering, Project Management, Erection & Commissioning of HFO Installation for 2 x 1.38 MW, 6.6 KV DG Sets for Ministry of Energy & Hydraulics, Republic of Guinea.
Location: Kankan, Guinea
Fuel: HFO
DG Set: Wartsila 2 x 1.38 MW
Completion Date: January, 2012.
Location: DLF Bldg.No.10, Gurgaon
4 x 5.5 MW, 11 kV,
Fuel: HSD / Natural Gas
GTG Package: 4 x 5.5 MW, Turbomach
Scope of Supply & Work: Liquid Fuel Handling System, Piping, Ventillation Ducting
Completion Date: January, 2010.
Engineering, Supply & Installation of 2 x 4.2 MW HFO based Wartsila Power Plant.
Location: Magadi, Kenya
8.4 MW, 11 kV,
Fuel: HFO, 180 cst
HFO DG Set : 4.2 MW, Wartsila
Completion Date – January, 2011
Dismantling of 2 x 4.2 MW HFO based Wartsila Power Plant.
Location: Haldia, West Bengal
8.4 MW, 11 kV,
Fuel: HFO
HFO DG Set : 4.2 MW, Wartsila
Completion Date – March, 2009
For their Diesel Engine Manufacturing factory
Location: Manesar, Haryana
3 x 12.9 MW GTG , 11 kV,
Fuel: HSD / Natural Gas
GTG Package : 3 x 12.9 MW, Siemens
Commissioning : Completed on February, 2009
Scope of Work : Complete Balance of Plant, Engineering, Supply & Erection including Mechanical & Electrical Equipments, HSD Fuel Tank Farm, Pump House, Piping, Approvals from CCOE.
Completion Date – February, 2011
For their green field Automobiles & Diesel Engine Manufacturing factory.
Location: Manesar, Haryana
20.5 MW, 11 kV, 30 Tons / Hr. Steam,
Fuel: HSD / Natural Gas
GTG Package: 3 x 5.5 MW, Turbomach
HFO DG Set: 1 MW, Cummins
1st Phase of Commissioning: Completed
Scope of Work: HSD Fuel Tank Farm, Pump House, Piping, Civil work for Tank Farm, Approvals from CCOE, Erection of 1 MW DG Set, Supply, Fabrication & Erection of Chimney for 1 MW DG Set, Supply of Cables, Control Panels, Earthing Pits, etc
Completion Date – March, 2006
A division of Toyota Kirloskar India Ltd.
For their Automobile and Body Building Factory
Location : Bidadi, Bangalore
2 MW, 11 kV and in parallel with Karnataka State electricity Board
Fuel : LSHS
Engine : Diahatsu Diesel, Japan
Alternator : 11 kV, Toyodenki, Japan
Scope : Complete EPC
Working Since February 2005
Revamping of their existing Chemical & Pharmaceutical Plant
Location : Vapi, Gujarat
Scope of Work : Upgradation of 11 kV Switchyard, Supply & Installation of new Power Transformer, Supply & Installation of LT Bus Duct, Supply & Installation of Power and Motor control Cubicle for the complete factory.
Installation of 1250 kVA HSD DG Set, Supply & Installation of Control Panels, Complete Civil Work for the Switchyard, Power Transformer, Control Room, Shed for DG Set, Shed for 8 Ton Furnace Oil Fired Boiler & Provision of Captive Power Plant
Complete Architectural, Civil, Mechanical & Electrical Engineering
Liasioning with Pollution Control Board, Electrical Inspectorate Approval
Completion Date: September, 2004
Location: BANGALORE Airport
2MW / 11 kV Synchronized with Karnataka State Electricity Board
FO Based DG set on LSHS
Installation Completed in 6 months including Civil Works
Engine – Hyundai Heavy Industries Ltd., Korea
Alternator: 11 kV, Hyundai Electric Ltd.
Working: Since March 2004
Scope of Work: Complete EPC including Civil Works
Completion Date: October, 2003
For 160 MW Power Plant
Location : Hazira – Gujarat
Will supply a complete HSD treatment plant
Purifiers – Mitsubishi – Japan
Completion Date: January, 2003
For their Chemical Plant Location : Baroda 1 x 4.2 MW / 11 KV 11 KV Distribution system with PLC based Load Management Steam – 15 TPH Fuel - Natural Gas Turbine – Tuma – Swiss & Solar – USA Alternator – Lerroy Somer – France Completion Date: February, 2002
For their Textiles Spinning Plant
Location : Silvassa
10 MW / 415 V ( 6 x 2080 KVA )
Fuel - Furnace Oil
Engine – AB Corporation – Belgium
Alternator – Lerroy Somer – France
Completion Date: December, 2001
For their Global R & D centre
Location : Bangalore
5 MW / 11 KV
DG set on LSHS
Completed in record time of 7 months
Engine – Niigata - GE – USA
Alternator – Nissishiba - Japan
Completion Date: November, 2000
For their Chemical Plant
Location : Surat
6.9 MW / 11 KV
11 KV Distribution system with PLC based Load Management
33 KV synchronizing with GEB
Steam – 20 TPH
Fuel - Natural Gas
Turbine – Tuma – Swiss & Solar – USA
Alternator – Lerroy Somer – France
Completion Date: May, 2000
For 350 MW Power Plant
Location: Kondapalli – Andhra Pradesh
Supplied complete HSD treatment plant
Purifiers – Mitsubishi – Japan
Completion Date: March, 1999
For their Ceramic Plant Location : Kadi - Gujarat 1.5 MW / 415 V Fuel - Natural Gas DG set – Caterpillar – USA Alternator – Caterpillar – India Completion Date: January, 1999
For their Cement Plant Location : Jafrabad 2 x 4 MW + 1 x 2.5 MW / 11 KV Fuel - Furnace Oil DG set – Niigata - Japan Toyo Denki – Japan Completion Date: June, 1998