Our Projects

 

110 KV Oyo-Mossaka Transmission Line - ROC
110 KV Oyo-Mossaka Transmission Line - ROC

110 KV Oyo-Mossaka Transmission Line - ROC

Civil work for Foundation, Erection of Transmission Towers & Conductor Stringing

Location : Republic of Congo.
Commissioning: October, 2018.

Kirloskar Oil Engines Ltd.
Kirloskar Oil Engines Ltd.
Kirloskar Oil Engines Ltd.
Kirloskar Oil Engines Ltd.

Kirloskar Oil Engines Ltd.

Erection & Commissioning of 1 x 3.15 MW DG Sets at BCPL - Dibrugarh

Location: Dibrugarh, Assam.
Fuel: HFO
DG Set: Kirloskar, 1 No. x 3.15 MW
Commissioning: March, 2014.

Kirloskar Oil Engines Ltd.
Kirloskar Oil Engines Ltd.

Kirloskar Oil Engines Ltd.

Erection & Commissioning of 1 x 2.5 MW DG Sets at IFFCO

Location: Phulpur, U.P.
Fuel: HFO
DG Set: Kirloskar, 1 No. x 2.5 MW
Commissioning: December, 2012.

Kirloskar Oil Engines Ltd.
Kirloskar Oil Engines Ltd.
Kirloskar Oil Engines Ltd.

Kirloskar Oil Engines Ltd.

Erection & Commissioning of 2 x 2.5 MW DG Sets at GNFC

Location: Dahej, Gujarat
Fuel: HFO
DG Set: Kirloskar, 2 Nos. x 2.5 MW
Commissioning: December, 2012.

Lubrizol India Ltd.
Lubrizol India Ltd.

Lubrizol India Ltd.

Dismantling of Existing Flare Stack, Supply of Material & Erection of New Flare Stack.

Location: Navi Mumbai
Fuel: HFO
DG Set: Caterpillar 7 Nos. x 14 MW
Commissioning: May, 2012.

Dipon Infrastructure Ltd.
Dipon Infrastructure Ltd.
Dipon Infrastructure Ltd.
Dipon Infrastructure Ltd.
Dipon Infrastructure Ltd.
Dipon Infrastructure Ltd.
Dipon Infrastructure Ltd.
Dipon Infrastructure Ltd.
Dipon Infrastructure Ltd.
Dipon Infrastructure Ltd.
Dipon Infrastructure Ltd.

Dipon Infrastructure Ltd.

Consultancy, Engineering, Project Management, Erection & Commissioning of HFO based Power Plant for 106 MW for M/s.Powerpac Mutiara.

Location: Keraniganj, Bangladesh
Fuel: HFO
DG Set: Caterpillar 7 Nos. x 14 MW
Commissioning: March, 2012.

Lucky Exports Ltd.
Lucky Exports Ltd.
Lucky Exports Ltd.

Lucky Exports Ltd.

Consultancy, Engineering, Project Management, Erection & Commissioning of HFO Installation for 2 x 1.38 MW, 6.6 KV DG Sets for Ministry of Energy & Hydraulics, Republic of Guinea.

Location: Kankan, Guinea
Fuel: HFO
DG Set: Wartsila 2 x 1.38 MW
Completion Date: January, 2012.

Turbomach India Pvt. Ltd.
Turbomach India Pvt. Ltd.
Turbomach India Pvt. Ltd.
Turbomach India Pvt. Ltd.
Turbomach India Pvt. Ltd.
Turbomach India Pvt. Ltd.

Turbomach India Pvt. Ltd.


Location: DLF Bldg.No.10, Gurgaon
4 x 5.5 MW, 11 kV,
Fuel: HSD / Natural Gas
GTG Package: 4 x 5.5 MW, Turbomach
Scope of Supply & Work: Liquid Fuel Handling System, Piping, Ventillation Ducting
Completion Date: January, 2010.

The Magadi Soda Co. Ltd.
The Magadi Soda Co. Ltd.
The Magadi Soda Co. Ltd.
The Magadi Soda Co. Ltd.
The Magadi Soda Co. Ltd.

The Magadi Soda Co. Ltd.

Engineering, Supply & Installation of 2 x 4.2 MW HFO based Wartsila Power Plant.

Location: Magadi, Kenya
8.4 MW, 11 kV,
Fuel: HFO, 180 cst
HFO DG Set : 4.2 MW, Wartsila
Completion Date – January, 2011

Tata Chemicals Ltd.
Tata Chemicals Ltd.
Tata Chemicals Ltd.
Tata Chemicals Ltd.
Tata Chemicals Ltd.
Tata Chemicals Ltd.
Tata Chemicals Ltd.

Tata Chemicals Ltd.

Dismantling of 2 x 4.2 MW HFO based Wartsila Power Plant.

Location: Haldia, West Bengal
8.4 MW, 11 kV,
Fuel: HFO
HFO DG Set : 4.2 MW, Wartsila
Completion Date – March, 2009

Maruti Suzuki Automobiles India Ltd.
Maruti Suzuki Automobiles India Ltd.
Maruti Suzuki Automobiles India Ltd.
Maruti Suzuki Automobiles India Ltd.

Maruti Suzuki Automobiles India Ltd.

For their Diesel Engine Manufacturing factory

Location: Manesar, Haryana
3 x 12.9 MW GTG , 11 kV,
Fuel: HSD / Natural Gas
GTG Package : 3 x 12.9 MW, Siemens
Commissioning : Completed on February, 2009
Scope of Work : Complete Balance of Plant, Engineering, Supply & Erection including Mechanical & Electrical Equipments, HSD Fuel Tank Farm, Pump House, Piping, Approvals from CCOE.
Completion Date – February, 2011

Maruti Suzuki Automobiles India Ltd.
Maruti Suzuki Automobiles India Ltd.
Maruti Suzuki Automobiles India Ltd.
Maruti Suzuki Automobiles India Ltd.

Maruti Suzuki Automobiles India Ltd.

For their green field Automobiles & Diesel Engine Manufacturing factory.

Location: Manesar, Haryana
20.5 MW, 11 kV, 30 Tons / Hr. Steam,
Fuel: HSD / Natural Gas
GTG Package: 3 x 5.5 MW, Turbomach
HFO DG Set: 1 MW, Cummins
1st Phase of Commissioning: Completed
Scope of Work: HSD Fuel Tank Farm, Pump House, Piping, Civil work for Tank Farm, Approvals from CCOE, Erection of 1 MW DG Set, Supply, Fabrication & Erection of Chimney for 1 MW DG Set, Supply of Cables, Control Panels, Earthing Pits, etc
Completion Date – March, 2006

Toyota Techno Park India Pvt. Ltd.
Toyota Techno Park India Pvt. Ltd.

Toyota Techno Park India Pvt. Ltd.

A division of Toyota Kirloskar India Ltd.
For their Automobile and Body Building Factory

Location : Bidadi, Bangalore
2 MW, 11 kV and in parallel with Karnataka State electricity Board
Fuel : LSHS
Engine : Diahatsu Diesel, Japan
Alternator : 11 kV, Toyodenki, Japan
Scope : Complete EPC
Working Since February 2005

Perstorp Aegis Chemicals Pvt. Ltd.
Perstorp Aegis Chemicals Pvt. Ltd.

Perstorp Aegis Chemicals Pvt. Ltd.

Revamping of their existing Chemical & Pharmaceutical Plant

Location : Vapi, Gujarat
Scope of Work : Upgradation of 11 kV Switchyard, Supply & Installation of new Power Transformer, Supply & Installation of LT Bus Duct, Supply & Installation of Power and Motor control Cubicle for the complete factory.
Installation of 1250 kVA HSD DG Set, Supply & Installation of Control Panels, Complete Civil Work for the Switchyard, Power Transformer, Control Room, Shed for DG Set, Shed for 8 Ton Furnace Oil Fired Boiler & Provision of Captive Power Plant
Complete Architectural, Civil, Mechanical & Electrical Engineering
Liasioning with Pollution Control Board, Electrical Inspectorate Approval
Completion Date: September, 2004

Hindustan Aeronautics Ltd – Bangalore

Location: BANGALORE Airport

2MW / 11 kV Synchronized with Karnataka State Electricity Board
FO Based DG set on LSHS
Installation Completed in 6 months including Civil Works
Engine – Hyundai Heavy Industries Ltd., Korea
Alternator: 11 kV, Hyundai Electric Ltd.
Working: Since March 2004
Scope of Work: Complete EPC including Civil Works
Completion Date: October, 2003

Gujarat State Electricity Generation Limited

For 160 MW Power Plant

Location : Hazira – Gujarat
Will supply a complete HSD treatment plant
Purifiers – Mitsubishi – Japan
Completion Date: January, 2003

Ambalal Sarabhai Limited
Ambalal Sarabhai Limited

Ambalal Sarabhai Limited

For their Chemical Plant

Location : Baroda
1 x 4.2 MW / 11 KV
11 KV Distribution system with PLC based Load Management
Steam – 15 TPH
Fuel - Natural Gas
Turbine – Tuma – Swiss & Solar – USA
Alternator – Lerroy Somer – France
Completion Date: February, 2002

Krishna Knitwear Industries Ltd.
Krishna Knitwear Industries Ltd.

Krishna Knitwear Industries Ltd.

For their Textiles Spinning Plant

Location : Silvassa
10 MW / 415 V ( 6 x 2080 KVA )
Fuel - Furnace Oil
Engine – AB Corporation – Belgium
Alternator – Lerroy Somer – France
Completion Date: December, 2001

GE - ITC
GE - ITC
GE - ITC
GE - ITC
GE - ITC
GE - ITC
GE - ITC
GE - ITC

GE - ITC

For their Global R & D centre

Location : Bangalore
5 MW / 11 KV
DG set on LSHS
Completed in record time of 7 months
Engine – Niigata - GE – USA
Alternator – Nissishiba - Japan
Completion Date: November, 2000

Pandesara Industries Limited
Pandesara Industries Limited

Pandesara Industries Limited

For their Chemical Plant

Location : Surat
6.9 MW / 11 KV
11 KV Distribution system with PLC based Load Management
33 KV synchronizing with GEB
Steam – 20 TPH
Fuel - Natural Gas
Turbine – Tuma – Swiss & Solar – USA
Alternator – Lerroy Somer – France
Completion Date: May, 2000

Kondapalli Power Corporation Ltd.

For 350 MW Power Plant

Location: Kondapalli – Andhra Pradesh
Supplied complete HSD treatment plant
Purifiers – Mitsubishi – Japan
Completion Date: March, 1999

Madhusudhan Ceramics Ltd.
Madhusudhan Ceramics Ltd.

Madhusudhan Ceramics Ltd.

For their Ceramic Plant

Location : Kadi - Gujarat
1.5 MW / 415 V
Fuel - Natural Gas
DG set – Caterpillar – USA
Alternator – Caterpillar – India
Completion Date: January, 1999

Narmada Cements Limited Larsen & Toubro Ltd
Narmada Cements Limited Larsen & Toubro Ltd

Narmada Cements Limited Larsen & Toubro Ltd

For their Cement Plant

Location : Jafrabad
2 x 4 MW + 1 x 2.5 MW / 11 KV
Fuel - Furnace Oil
DG set – Niigata - Japan
Toyo Denki – Japan
Completion Date: June, 1998